1501 South Main Street Fairfield, IA 52556 Phone 641-472-5145 Fax 641-472-2653 E-Mail email@french-reneker.com |
| STORM SEWER - LIBERTYVILLE | |||
|
|
|||
|
Pipe Installation |
|||
|
Construction work began recently on proposed storm sewer improvements within the city of Libertyville. The improvements include 2,521 linear feet of storm sewer ranging in size from 12-inch diameter to 24-inch diameter along with 15 manholes and intakes to improve drainage within the city of Libertyville. Also included is nearly 8,000 linear feet of roadway ditch construction to enhance drainage.
|
|||
|
|
|||
|
Prefabricated Intake and Manhole Sections |
|||
|
The city of Libertyville has a very flat topography and has been plagued in the past by localized flooding which has caused frequent property damage. French-Reneker-Associates assisted in the preparation of a Community Development Block Grant Public Facilities Application that was successful in securing grant funds for this project.
|
|||
|
|
|||
|
High Density Polyethylene Pipe Materials |
|||
|
Construction
on the $170,000 construction contract is being done by Rock Kreek Spread of
West Point, Iowa. Work is
scheduled for completion in the spring of 2003.
|
|||
|
|
|||
|
|
|||